New Orleans Airport
New Airport North Terminal Expansion electrical work that includes:
New Substations and Generators:
- Supply and Install 4 @ 3,800KW Med Volt Power Generators
- Supply and Install Terminals, Concourses, Parking, Utility Building Substations, Substations Bus Ducts
Parking Garage Electrical Work:
- New Electrical Work and Electrical Repairs (Lighting, Power, HVAC Power)
- Deck and Perimeter Lighting
- Branch Power
- Power Feeders and Electrical gear
- Telecommunications and Security Systems Rough-In
- Approximately 800,000 Sq. Ft, 1,800 Parking Spaces
- Facility Access Control & Video Surveillance System